AI- 52627
Purchasing Department   11.C.
CC CONSENT
Meeting Date:
12/15/2015
Submitted For:
Marcie Jackson
Submitted By:
Moises Salazar, PURCHASING DEPT.
Department:
COMM. PCT. #1

Information

CAPTION

Ratification of fully executed Change Order No. 8 in connection to contract No. C-14-362-10-28 with 2GS, LLC for the project: -Hidalgo County Precinct #1 -SIOUX ROAD PAVING & DRAINAGE IMPROVEMENTS PROJECT [from Tower Road to Val Verde Road] as recommended by  Mr. Raul Sesin, P.E.

BACKGROUND

Additional 46 calendar days due to utility lines delay and rain days for project completion.

Fiscal Impact

FISCAL YEAR:
2015
ACCT. #:
5-13XX-431-00-121-183-X-721
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

NO additional cost to project; Time extension = 46 calendar days; PO #717811 for 2GS, LLC; funds available as of 12-11-15.



Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 12/11/2015 04:33 PM
Budget and Management Veronica Ortiz 12/11/2015 04:44 PM
Auditor's Office Monica Salinas 12/11/2015 05:42 PM
Form Started By:
moysalazar
Started On:
12/10/2015 11:47 AM
Final Approval Date:
12/11/2015