AI- 53197
Purchasing Department   12.D.
CC CONSENT
Meeting Date:
02/03/2016
Submitted For:
Comm. Cuellar
Submitted By:
Katia Garcia, COMM. PCT. #1
Department:
COMM. PCT. #1

Information

CAPTION

Ratification of fully executed Change Order No. 9 in connection to contract No. C-14-362-10-28 with 2GS, LLC for the project:-Hidalgo County Precinct #1 - SIOUX ROAD PAVING & DRAINAGE IMPROVEMENTS PROJECT [from Tower Road to Val Verde Road] as recommended by Mr. Raul Sesin, P.E.

BACKGROUND

Additional 30 calendar days due to utility lines delay and rain days for project completion.

Fiscal Impact

FISCAL YEAR:
ACCT. #:
FUNDS AVAILABLE Y/N?:
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

NO additional cost to project; Time extension = 30 calendar days; PO# 717811 for 2GS, LLC.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 01/29/2016 02:49 PM
Budget and Management Veronica Ortiz 01/29/2016 03:41 PM
Auditor's Office Monica Salinas 01/29/2016 06:24 PM
Form Started By:
Katia Garcia
Started On:
01/29/2016 10:50 AM
Final Approval Date:
01/29/2016