AI- 5327
13.K.1.
CC REGULAR
- Meeting Date:
- 09/04/2007
- Submitted By:
- Laura Moya, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
Information
CAPTION
Presentation for consideration, discussion acceptance and approval of Change Order No 1 for Southfork Estates C-CAP-07-010-03-07 for material and work adjustments in the amount of $13,824.00 (increase) project engineer is Hinojosa Engineering, Inc., and contractor is Jimmy Closner & Sons Construction Co., a Border Colonia Access Program Project(s).
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2007
- ACCT. #:
- 7-1311-431-00-122-683-0-733
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Available account balance is $ 108,385.20 as of 08/30/07.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 08/29/2007 09:03 PM |
| Budget and Management | Dina Trevino | 08/30/2007 03:13 PM |
| Auditor's Office | 08/31/2007 05:17 PM |
- Form Started By:
- lmoya
- Started On:
- 08/29/2007 03:54 PM
- Final Approval Date:
- 08/31/2007