A. Recommendation by project engineer, TEDSI  Infrastructure Group, to award the Base Bid to the responsible vendor submitting the lowest and best bid meeting all specifications:
 
Bid Number & 
Project Name
Recommended
Vendor
Total
Amount
RFB: 2016-289-08-31-Nittler Road IOC Company $1,167,775.65
RFB: 2016-290-08-31-Mile 9 North Bearkat Construction, LLC $648,048.00
 
B. Pursuant to TXLGC 262.031 and in the interest of expediting a project's progress, requesting authority - approval for the Precinct Commissioner or designee: Raul Lozano, to execute change orders that involve...'an increase or decrease in cost of $50,000.00 or LESS and in no event to exceed the Change Order's statutory limits...'. The original contract price may not be decreased by 18% or more without the consent of the contractor".

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2016
ACCT. #:
6-1280-431-00-121-801/807/809-5-721
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Funds available as of 09/02/2016, in accounts:
Nittler Rd. 6-1280-431-00-121-801-5-721 in the amount of $1,390,176.78
Mile 9 6-1280-431-00-121-807-5-721 in the amount of $383,181.96
Mile 9 6-1280-431-00-121-809-5-721 in the amount of $379,967.02

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal Letty Saenz 09/02/2016 09:28 AM
Budget and Management Veronica Ortiz 09/02/2016 09:38 AM
Final Approval Monica Salinas 09/02/2016 04:52 PM
Form Started By:
Yolanda Velasquez
Started On:
09/02/2016 09:04 AM
Final Approval Date:
09/02/2016