CAPTION

A.  Requesting acceptance and approval of a Substantial Completion date of September 12, 2016 for the Mile 2 North Road Project Contract #14-153-02-17, IOC Company LLC.

B.  As requested and instructed by HC Auditor's Office , acceptance and approval of  heavy traffic days suspension of work  as submitted by awarded Contractor. IOC Company, LLC [thru Contract #14-153-02-17] to  L&G Engineering, project engineer including e-mail accounting for an additional three [3] days [through an oversight by engineer and not contractor] for Mile 2 North Road Project in connection with the attempt to impose/charge liquidated damages prior to processing invoices.

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 04/12/2017 01:17 PM
Budget and Management Veronica Ortiz 04/12/2017 01:28 PM
Final Approval Monica Salinas 04/13/2017 05:22 PM
Form Started By:
nceballos
Started On:
04/11/2017 12:26 PM
Final Approval Date:
04/13/2017