AI - 59419
17.
DRAINAGE DISTRICT
- Meeting Date:
- 04/18/2017
- Submitted For:
- Claudette Guerrero
- Submitted By:
- Claudette Guerrero, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
2013 Bonds
Budget: 330-East Donna Drain
A. Approval of Change Order No. 1 from Mor-Will, LLC in the amount of $$28,000.00 and an additional (10) ten days to Construction Contract No. C-HCDD1-16-040-08-16 Drainage Improvement Project East Donna Drain Flood Pump.
B. Application for Payment No. 2 in the amount of $72,195.75 from Mor-Will, LLC pertaining to Construction Contract No. C-HCDD1-16-040-08-16-Drainage Improvement Project-East Donna Drain Flood Pump.
PO#630511.
Project Engineer: Mark Corbitt, P.E.-Tedsi Infrastructure Group
Budget: 345-Mercedes Lateral
C. Application for Payment No. 2 in the amount of $180, 149.12 from Mor-Will, LLC pertaining to Construction Contract No. C-HCDD1-16-039-08-16 Drainage Improvement Project Mercedes Lateral Flood Pump.
PO#627491
Project Engineer: Mark Corbitt, P.E.-Tedsi Infrastructure Group.
Budget: 365-Rural Drainage Development Pct.4
D. Approval of Change Order No. 2 from Venser Contractors, LLC for an additional 30 days to Construction Contract No. HCDD1-16-045-09-27-Kenyon Rd. & Mile 17 Area Drainage Improvements.
E. Application for Payment No. 2 in the amount of 59,005.61 from Venser Contractors, LLC pertaining to Construction Contract HCDD1-16-045-09-27 Kenyon Rd & Mile 17 Area Drainage Improvements.
PO#630834
Budget: 330-East Donna Drain
A. Approval of Change Order No. 1 from Mor-Will, LLC in the amount of $$28,000.00 and an additional (10) ten days to Construction Contract No. C-HCDD1-16-040-08-16 Drainage Improvement Project East Donna Drain Flood Pump.
B. Application for Payment No. 2 in the amount of $72,195.75 from Mor-Will, LLC pertaining to Construction Contract No. C-HCDD1-16-040-08-16-Drainage Improvement Project-East Donna Drain Flood Pump.
PO#630511.
Project Engineer: Mark Corbitt, P.E.-Tedsi Infrastructure Group
Budget: 345-Mercedes Lateral
C. Application for Payment No. 2 in the amount of $180, 149.12 from Mor-Will, LLC pertaining to Construction Contract No. C-HCDD1-16-039-08-16 Drainage Improvement Project Mercedes Lateral Flood Pump.
PO#627491
Project Engineer: Mark Corbitt, P.E.-Tedsi Infrastructure Group.
Budget: 365-Rural Drainage Development Pct.4
D. Approval of Change Order No. 2 from Venser Contractors, LLC for an additional 30 days to Construction Contract No. HCDD1-16-045-09-27-Kenyon Rd. & Mile 17 Area Drainage Improvements.
E. Application for Payment No. 2 in the amount of 59,005.61 from Venser Contractors, LLC pertaining to Construction Contract HCDD1-16-045-09-27 Kenyon Rd & Mile 17 Area Drainage Improvements.
PO#630834
BACKGROUND
Fiscal Impact
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 04/13/2017 04:27 PM |
- Form Started By:
- ccavazos
- Started On:
- 04/13/2017 10:58 AM
- Final Approval Date:
- 04/13/2017