AI - 6571
4.
DRAINAGE DISTRICT
- Meeting Date:
- 11/20/2007
- Submitted For:
- Lora Briones
- Submitted By:
- Jaime Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
A.) Requesting approval of Change Order # 1 for the "North San Juan Lateral Alberta Road Crossing" for supplies added to the project in the amount of $2,600.00.
Project Engineer: R. Gutierrez Engineering Corporation.
Contractor: Dos Logistics, Inc.
B.) Requesting approval of Budget Amendment to the District Capital Projects to fund the aforementioned change order.
C.) Requesting approval of Change Order # 1 for the "HCDD1, PCT.4 Sanitary Sewer Line" for the open cut on Doolittle Road in the amount of $6764.00.
Project Engineer: Quintanilla, Headley & Associates.
Contractor: United Contracting.
D.) Requesting approval of Budget Amendment to the General Fund for the aforementioned change order.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Dina Trevino | 11/15/2007 03:52 PM |
| Court Administrator | Monica Salinas | 11/15/2007 04:50 PM |
- Form Started By:
- Jaime Salazar
- Started On:
- 11/14/2007 04:33 PM
- Final Approval Date:
- 11/15/2007