AI - 67598
8.
DRAINAGE DISTRICT
- Meeting Date:
- 11/20/2018
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Requesting approval of Change Order No. 5 reflecting an increase in the amount of $96,346.00, and 60 contract days, in connection with Contract No. C-HCDD1-18-003-02-06 -Hidalgo County Drainage District No. 1 "Alamo Lateral & Cesar Chavez Drain Phase II Improvements (North of Canton Crossing, Canton Crossing, Alberta Crossing & Tower Crossing" with Venser Contractors, LLC, as recommended by HCDD1 Engineer, Mr Noe Saldivar, P.E., and approved by Mr. Raul E. Sesin, P.E., CFM. HCDD1 General Manager.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 11/16/2018 05:13 PM |
- Form Started By:
- moysalazar
- Started On:
- 11/08/2018 11:45 AM
- Final Approval Date:
- 11/16/2018