AI - 68707
8.B.
DRAINAGE DISTRICT
- Meeting Date:
- 01/29/2019
- Submitted For:
- Claudette Guerrero
- Submitted By:
- Claudette Guerrero, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Approval to issue payment on the following items proceeding review & compliance of contract terms & conditions:
CIP 133-2012 Bonds
Bdgt: 300-J09 Drain
Application for Payment No. 4 in the amount of $112,395.92 from Castle Enterprises, LLC pertaining to Construction Contract No. HCDD1-18-020-05-08 J09 Phase 3 Drainage Improvements.
Project Engineer: Jason M. Adams, P.E.-Tedsi Infrastructure - PO#634761
CIP 133-2012 Bonds
Bdgt: 300-J09 Drain
Application for Payment No. 4 in the amount of $112,395.92 from Castle Enterprises, LLC pertaining to Construction Contract No. HCDD1-18-020-05-08 J09 Phase 3 Drainage Improvements.
Project Engineer: Jason M. Adams, P.E.-Tedsi Infrastructure - PO#634761
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 01/25/2019 05:46 PM |
- Form Started By:
- ccavazos
- Started On:
- 01/25/2019 03:35 PM
- Final Approval Date:
- 01/25/2019