AI - 72064
3.C.
DRAINAGE - CONSENT SPECIAL
- Meeting Date:
- 09/10/2019
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the fully executed Change Order No. 1 reflecting an increase in the total amount of $19,500.00, and Five (5) additional construction calendar days, in connection with contract No. C-HCDD1-19-002-01-09 -Hidalgo County Drainage District No. 1 "Pharr-Mcallen Drain Improvements -2018 Bond Referendum Project #31" with Mor-Wil, LLC, as recommended by project engineer L&G Engineering, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM., subject to compliance to HB1295.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 09/06/2019 06:21 PM |
- Form Started By:
- moysalazar
- Started On:
- 08/30/2019 02:43 PM
- Final Approval Date:
- 09/06/2019