AI - 73354
5.B.
DD-CONSENT AGENDA REGULAR MTG
- Meeting Date:
- 11/26/2019
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
CAPTION
Ratification of the fully executed Change Order No. 2 reflecting Six (6) additional construction calendar days, in connection with the contract No. C-HCDD1-19-054-07-30 -Hidalgo County Drainage District No. 1 "Willacy County Relief Channel Overflow Structure Improvements" with RDH Site and Concrete, LLC, as recommended by project engineer Jose Noe Saldivar, P.E., HCDD1 Engineer IV, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM., subject to compliance to HB1295.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 11/22/2019 05:49 PM |
- Form Started By:
- moysalazar
- Started On:
- 11/21/2019 10:07 AM
- Final Approval Date:
- 11/22/2019