AI - 73356
5.C.
DD-CONSENT AGENDA REGULAR MTG
- Meeting Date:
- 11/26/2019
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
CAPTION
Ratification of the fully executed Change Order No. 2, reflecting ninety-seven (97) additional construction calendar days, in connection with contract No. C-HCDD1-19-036-05-07 -Hidalgo County Drainage District No. 1 "Iowa Road Drainage Improvements Project" with Castle Enterprises, LLC, as recommended by project engineer, Jose Noe Salvidar, P.E., HCDD1 Engineer IV, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM. (subject to compliance with HB1295).
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 11/22/2019 05:49 PM |
- Form Started By:
- moysalazar
- Started On:
- 11/21/2019 10:53 AM
- Final Approval Date:
- 11/22/2019