CAPTION
Budget 300-J09 Drain
1. Approval of Certificate of Construction Completion from Castle Enterprises, LLC pertaining to Construction Contract No. HCDD1-18-020-05-08 J09 Phase III Drain Improvement.
2. Approval of Application for Payment No. 11-Retainage in the amount of $132,577.47 from Castle Enterprises, LLC pertaining to Construction Contract No. HCDD1-18-020-05-08 J09 Phase III Drain Improvements.
Engineer: Jose N. Saldivar, P.E. -HCDD1 (Previously Tedsi Infrastructure Group)
PO#634761
1. Approval of Certificate of Construction Completion from Castle Enterprises, LLC pertaining to Construction Contract No. HCDD1-18-020-05-08 J09 Phase III Drain Improvement.
2. Approval of Application for Payment No. 11-Retainage in the amount of $132,577.47 from Castle Enterprises, LLC pertaining to Construction Contract No. HCDD1-18-020-05-08 J09 Phase III Drain Improvements.
Engineer: Jose N. Saldivar, P.E. -HCDD1 (Previously Tedsi Infrastructure Group)
PO#634761
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 01/10/2020 05:20 PM |
- Form Started By:
- ccavazos
- Started On:
- 01/10/2020 12:45 PM
- Final Approval Date:
- 01/10/2020