AI- 74595
Purchasing Department 13.A.
CC CONSENT AGENDA SPECIAL MTG
Prct. 2
- Meeting Date:
- 02/26/2020
- Submitted For:
- Eddie Cantu
- Submitted By:
- Erika Zamora, COMM. PCT. #2
- Department:
- COMM. PCT. #2
CAPTION
Requesting approval of Change Order Nos. 1 through 3 (C-19-017-11-15) with 2GS, LLC dba Earthworks Enterprise for the Hidalgo County Precinct #2 - Dicker Road Reconstruction Project from (23rd Street to Jackson Road) as recommended by the project engineer, Saul Muñoz, P.E.
BACKGROUND
CO #1-Modify Traffic Control Plan from 23rd to 10th St and reduce construction cost;
CO #2-additional culverts needed due to plan error;
CO #3-waterline construction work added through ICA between County and Mcallen PUB
Change Orders 1 through 3 will increase the contract $287,083.94.
CO #2-additional culverts needed due to plan error;
CO #3-waterline construction work added through ICA between County and Mcallen PUB
Change Orders 1 through 3 will increase the contract $287,083.94.
Fiscal Impact
- CALENDAR YEAR:
- 2020
- ACCT. #:
- 0-1315-431-00-122-062-0-721
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Funding for Change Order No. 1 and 2 will be covered within the current PO.Funding for Change Order No. 3 will be provided by Mcallen PUB within 30 days of executing the change order as provided in the interlocal agreement approved by CC 6/6/19 AI#70659.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 02/21/2020 05:50 PM |
| Final Approval | Monica Salinas | 02/21/2020 05:56 PM |
- Form Started By:
- Erika Zamora
- Started On:
- 02/21/2020 04:26 PM
- Final Approval Date:
- 02/21/2020