Information
CAPTION
Requesting approval of Change Order No. 2 reflecting an increase in the amount of $201,914.94, and One Hundred and Eighteen (118) additional construction calendar days, in connection with contract No. C-HCDD1-20-002-02-11 -Hidalgo County Drainage District No. 1 " Mission Inlet Drainage Improvements Project (Section C & F-Balboa Estates Area Drainage Improvements)" with Castle Enterprises, LLC, as recommended by project engineer, L&G Engineering (subject to compliance to HB1295).