AI - 80374
3.C.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 04/13/2021
- Submitted For:
- Jaime Salazar
- Submitted By:
- Rocio Villarreal, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the fully executed Change Order No. 1 reflecting twenty-one (21) additional construction calendar days, in connection with Contract C-HCDD1-20-043-09-15-"Malone Drive & Pomelo Road -2018 Bond Referendum Project #18" with Venser Contractors, LLC, and as recommended by Project Engineer, Guzman & Munoz Engineering & Surveying, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM. (subject to compliance to HB1295)