Requesting approval of Change Order No. 5 reflecting a decrease in the amount of - ($84,150.00), and an increase of twenty-three (23) construction calendar days, in connection with contract No. C-HCDD1-19-074-11-26 -Hidalgo County Drainage District No. 1 "Mission Lateral (Section I) -2018 Bond Referendum project #26" with Saenz Brothers Construction as recommended by project engineer, Damien B. Tijerina, P.E., L&G Engineering (subject to compliance to HB1295).