Jackson Road Drain Phase I - Budget 516
1. Approval of Application for Payment No. 3 in the amount of $197,965.95 from G&G Contractors pertaining to construction contract No. C-HCDD1-20-034-08-11. Project Engineer Quintanilla, Headley & Associates, Inc. PO#640613-21

PD Lateral Phase I - Budget 529
2. Approval of Application for Payment No. 5 in the amount of $198,921.77 from Mor-Wil, LLC. pertaining to construction contract No. HCDD1-20-026-06-23. Project Engineer Izaguirre Engineering. PO#640211-21

3. Approval of Application for Payment No. 6 in the amount of $151,042.17 from Mor-Wil, LLC. pertaining to construction contract No. HCDD1-20-026-06-23. Project Engineer Izaguirre Engineering. PO#640211-21

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 06/11/2021 05:26 PM
Form Started By:
Alvaro Chuc
Started On:
06/09/2021 11:12 AM
Final Approval Date:
06/11/2021