AI - 82024
5.B.
DD-CONSENT AGENDA REGULAR MTG
Meeting Date:
08/24/2021
Submitted For:
Jaime Salazar
Submitted By:
Rocio Villarreal, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

CAPTION

Ratification of the fully executed Change Order No. 5 reflecting a net increase of $6,250.00, and an additional nineteen (19) construction calendar days, in connection with Contract C-HCDD1-20-042-09-08, Mission Lateral Section II -2018 Bond Referendum Project #26 with H&R Lease Services, LLC, as recommended by Project Engineer, L&G Engineering and approved HCDD1 General Manager, Raul E. Sesin, P.E., CFM.