AI - 82330
5.B.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 09/07/2021
- Submitted For:
- Jaime Salazar
- Submitted By:
- Rocio Villarreal, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the fully executed Change Order No. 3 reflecting an increase in the amount of $43,909.20, and additional twenty-seven (27) construction calendar days, in connection with the Contract C-HCDD1-20-040-09-08 -"3 3/4 Mile Rd. & Schuerbach Rd -2018 Bond Referendum Project #2" with Gonzalez Engineering & Management, LLC, as recommended by Project Engineer, Javier Hinojosa Engineering, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 09/03/2021 05:06 PM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 09/03/2021 02:27 PM
- Final Approval Date:
- 09/03/2021