AI - 83402
5.D.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 11/16/2021
- Submitted For:
- Jaime Salazar
- Submitted By:
- Rocio Villarreal, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Requesting approval of Change Order No. 1 reflecting an increase in the amount of $317,792.37, with an additional one hundred fifty (150) construction calendar days, in connection with Contract C-HCDD1-21-011-07-27 "Cesar Chavez & Texas Road, Canton Rd & Tower Rd, and Iowa Rd Drainage Areas Improvements" with Mor-Wil, LLC, as recommended by District Engineer.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Jaime Salazar | 11/12/2021 04:31 PM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 11/12/2021 02:08 PM
- Final Approval Date:
- 11/12/2021