CAPTION

Requesting approval of Change Order No. 1 reflecting an increase in the amount of $77,272.12, with an additional two hundred sixty (260) construction calendar days, in connection with Contract C-HCDD1-20-009-07-07 "South Lateral Drain Improvements Phase I (McColl Road to San Juan Road)-2018-Bond Referendum Project #34" with Castle Enterprises, LLC, as recommended by L&G Engineering.