CAPTION
Requesting approval of Change Order No. 7 reflecting an increase in the amount of $90,640.00 , in connection with the Contract C-HCDD1-20-029-06-23-"PD Lateral (Phase II) -2018 Bond Referendum Project #29" with Mor-Wil, LLC, and as recommended by Project Engineer, Izaguirre Engineering Group.
BACKGROUND
HB1295 Form submitted.
Fiscal Impact