CAPTION
Requesting approval of Change Order No. 7 reflecting an increase in the amount of $60,109.36, and Ninety (90) additional construction calendar days, in connection with Contract No. C-HCDD1-20-002-02-11 -"Mission
Inlet Drainage Improvements Project (Section C & F-Balboa Estates Area Drainage Improvements)'' with Castle Enterprises, LLC, as recommended by Project Engineer, L&G Engineering.
Inlet Drainage Improvements Project (Section C & F-Balboa Estates Area Drainage Improvements)'' with Castle Enterprises, LLC, as recommended by Project Engineer, L&G Engineering.
BACKGROUND
Description:
-Contract Time Extension (90 days)
-Additional Excavation Quantities $60,109.36
Reason for Change Order:
-Delays due to property owner conflicts
-Weather delays
-Additional volume added to Mission Inlet Drain System
Compliance with HB 1295
-Contract Time Extension (90 days)
-Additional Excavation Quantities $60,109.36
Reason for Change Order:
-Delays due to property owner conflicts
-Weather delays
-Additional volume added to Mission Inlet Drain System
Compliance with HB 1295
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 05/27/2022 05:13 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 05/17/2022 11:42 AM
- Final Approval Date:
- 05/27/2022