CAPTION
Requesting approval of Change Order No. 2 reflecting an increase in the amount of $328,637.20, and One Hundred and Twenty (120) additional construction calendar days, in connection with Contract No. C-HCDD1-20-009-07-07 -"South Lateral Drain Improvements Phase I (McColl Rd to San Juan Rd) -2018 Bond Referendum Project No.34'' with Castle Enterprises, LLC, as recommended by Project Engineer, L&G Engineering. (Subject to compliance with HB-1295)
BACKGROUND
Reason for Change Order:
1. Additional day added for extra work and procurement of materials
2. Design changes to the South Lateral Drainage System
1. Additional day added for extra work and procurement of materials
2. Design changes to the South Lateral Drainage System
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 05/27/2022 05:13 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 05/27/2022 02:21 PM
- Final Approval Date:
- 05/27/2022