AI - 86762
6.F.
DD-REGULAR AGENDA REGULAR MTG
- Meeting Date:
- 07/26/2022
- Submitted By:
- Alvaro Chuc, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
CAPTION
PD Lateral Phase II - Budget 529
1. Requesting acceptance and approval of Certificate of Substantial Completion and Certificate of Construction Completion from Mor-Wil, LLC pertaing to PD Lateral Phase II Construction Contract C-HCDD1-20-029-06-23.
2. Approval of Application for Payment Retainage in the amount of $184,601.47 and $450.14 in interest from Mor-Wil, LLC pertaining to PD Lateral Phase II Construction Contract C-HCDD1-20-029-06-23. Project Engineer Izaguirre Engineering Group PO#640212
1. Requesting acceptance and approval of Certificate of Substantial Completion and Certificate of Construction Completion from Mor-Wil, LLC pertaing to PD Lateral Phase II Construction Contract C-HCDD1-20-029-06-23.
2. Approval of Application for Payment Retainage in the amount of $184,601.47 and $450.14 in interest from Mor-Wil, LLC pertaining to PD Lateral Phase II Construction Contract C-HCDD1-20-029-06-23. Project Engineer Izaguirre Engineering Group PO#640212
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 07/22/2022 05:32 PM |
- Form Started By:
- Alvaro Chuc
- Started On:
- 07/22/2022 03:06 PM
- Final Approval Date:
- 07/22/2022