AI- 8679
18.A.8.
CC REGULAR
Meeting Date:
04/07/2008
Submitted For:
Letty Saenz
Submitted By:
Letty Saenz, COMM. PCT. #4
Department:
PURCHASING DEPT.

CAPTION

Requesting approval of Change Order No. 1 (increase) in connection with the unforeseen discovery of three (3)  additional fuel tanks during the current/on-going "Demolition and Removal of Underground Petroleum Storage Tank System (located at 201 and 217 North Closner Blvd., Edinburg, Texas) for Hidalgo County in the amount of $10,500.00 from contracted vendor, Rio Tank Service Construction, Inc. and as recommended by project engineer, L & G Engineering, with authority for County Judge to execute document.

BACKGROUND

Change Order No. 1

Fiscal Impact

FISCAL YEAR:
2008
ACCT. #:
8-1336-419-40-220-028-0-739
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Amount available for PO #600071 is $45,000.00 as of 4-2-08.  Approval of Change Order #1 will increase cost an additional $10,500.00 for Rio Tank Service Construction, Inc. totaling $55,500.00.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 04/02/2008 11:54 AM
Budget and Management Dina Trevino 04/02/2008 01:05 PM
Auditor's Office 04/03/2008 04:43 PM
Form Started By:
Letty Saenz
Started On:
04/01/2008 03:41 PM
Final Approval Date:
04/03/2008