AI- 8811
15.H.1.
CC REGULAR
Meeting Date:
04/14/2008
Submitted By:
Laura Moya, PURCHASING DEPT.
Department:
PURCHASING DEPT.

CAPTION

Requesting approval of "Certificate of Construction Completion" submitted through project engineer TEDSI Infrastructure Engineering reflecting the completion date of March 5, 2008 for
1. RC Babb #1 - C-CAP-07-027-08-29
2. RC Babb #2 - C-CAP-07-028-08-29
3. RC Babb #3 - C-CAP-07-029-08-29
through awarded contractor IOC Company LLC.

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2008
ACCT. #:
FUNDS AVAILABLE Y/N?:
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Action item is in regards to CC 04/07/08 agenda item 8682. Prior to processing the requests to release retainage, Comissioners Court must approve the Certificates of Construction Completion.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 04/09/2008 05:30 PM
Budget and Management Dina Trevino 04/10/2008 08:25 AM
Rey Salazar Rey Salazar 04/10/2008 10:39 AM
Auditor's Office 04/10/2008 05:27 PM
Form Started By:
lmoya
Started On:
04/09/2008 11:55 AM
Final Approval Date:
04/10/2008