AI - 88905
4.C.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 12/20/2022
- Submitted For:
- Jaime Salazar
- Submitted By:
- Enriqueta Zambrano, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of approved and fully executed Change Order No. 7, in connection with the project "Jackson Rd Drain Phase I -2018 Bond Referendum Project No. 16’’, reflecting an increase of Sixty-One (61) additional construction calendar days to Contract No. C-HCDD1-20-034-08-11, with RG Enterprises, LLC dba G&G Contractors, as recommended by project engineer, Quintanilla Headley & Associates.
BACKGROUND
Contract Time Extension -61 additional days.
Weather & Supplier Delays.
Weather & Supplier Delays.
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 12/16/2022 04:42 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 12/16/2022 09:26 AM
- Final Approval Date:
- 12/16/2022