AI - 88916
3.A.
DD-CONSENT AGENDA SPECIAL MTG
Meeting Date:
12/20/2022
Submitted For:
Jaime Salazar
Submitted By:
Enriqueta Zambrano, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

Information

CAPTION

Ratification of the approved and fully executed Change Order No. 12 with Castle Enterprises, LLC (C-HCDD1-20-002-02-11) reflecting an additional sixteen (16) construction calendar days for, "Mission Inlet Balboa Estates Drainage Improvements Project (Section C&F)" and as recommended by Project Engineer, L&G Engineering, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM. 

BACKGROUND

Contract extension time
Weather days/final punch walk through

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 12/16/2022 04:42 PM