Information

CAPTION

Requesting approval of Change Order No. 1 & 2 (C-22-0094-09-06) with Go Underground, LLC for the Hidalgo County Precinct 2 Las Milpas Road Drainage, Bridge, and Traffic Signal Installation Project as recommended and as detailed by project engineer, Saul Muñoz, P.E.

BACKGROUND

Change Order No. 1 -Request for contract decrease in the amount of $328,176.60 due to RCP being order in advance and contractor only going to charge for labor and equipment
Change Order No. 1 - Request for contract increase in the amount of $21,700.00 to relocate a 12" waterline that had not been previously identified in plans.

Fiscal Impact

CALENDAR YEAR:
2023
ACCT. #:
3-1290-431-50-115-297-2-723
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

CSLFRF-SW-PCT2 LAS MILPAS RD-DRAINAG SYS; Funding available through PO#856776 in the amount of $3,694,806.64 as of 4/27/23.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal Dina Trevino 04/28/2023 04:08 PM
Budget and Management Veronica Ortiz 04/28/2023 04:14 PM
Final Approval Monica Salinas 04/28/2023 05:01 PM