AI - 90694
3.A.
DD-CONSENT AGENDA SPECIAL MTG
Meeting Date:
05/02/2023
Submitted For:
Jaime Salazar
Submitted By:
Enriqueta Zambrano
Department:
DRAINAGE DISTRICT

Information

CAPTION

Ratification of approved and fully executed Change Order No. 9, in connection with the project "Jackson Rd Drain Phase I -2018 Bond Referendum Project No. 16’’, reflecting an increase of Sixty (60) additional construction calendar days to Contract No. C-HCDD1-20-034-08-11, with RG Enterprises, LLC dba G&G Contractors, as recommended by Project Engineer, Quintanilla Headley & Associates.

BACKGROUND

Contract Time Extension -60 additional days due to Weather & Supplier Delays. (pump fittings, elbows, etc.)

Project completion date: June 24, 2023 for Change Order 9

 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 04/28/2023 04:08 PM
Form Started By:
Enriqueta Zambrano
Started On:
04/27/2023 03:46 PM
Final Approval Date:
04/28/2023