CAPTION
Requesting approval of Change Order No.3, reflecting an increase in the amount of $104,940.00, and ninety (90) additional construction calendar days, in connection with the project "Mission-McAllen Rado Phase I -2018 Bond Referendum Project No. 25’', Contract No. C-HCDD1-21-023-07-27, with Gonzalez Engineering & Management, LLC, as recommended by Project Engineer, B2Z Engineering, LLC.
BACKGROUND
Project completion date as per CO-3: August 22, 2023
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 05/26/2023 04:57 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 05/19/2023 08:26 AM
- Final Approval Date:
- 05/26/2023