Information
CAPTION
Ratification of the approved and fully executed Change Order No. 3 with Texas Cordia Construction, LLC. (C-HCDD1-22-003-02-22) reflecting an increase of $3,385.99 and thirty-eight (38) additional calendar days to the Mission-McAllen Rado Alternate-Phase II - 2018 Bond Referendum Project 25 as recommended by Project Engineer, B2Z Engineering, LLC. and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.