AI - 92434
6.A.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 09/19/2023
- Submitted For:
- Yvette Barrera
- Submitted By:
- Enriqueta Zambrano
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the approved and fully executed Change Order No.2, reflecting a decrease in the amount of ($12,845.96) and 120 additional construction calendar days, for "Mid-Valley Airport Ditch 18B Drainage Improvements - 2018 Bond Referendum Project No. 19’', Contract No. C-HCDD1-22-020-05-31, with Mor-Wil, LLC, as recommended by Project Manager, B2Z Engineering, LLC.and approved by HCDD1 District General Manager, Raul E. Sesin, P.E., CFM.
BACKGROUND
Project completion date: December 21, 2023
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 09/15/2023 04:02 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 09/12/2023 01:38 PM
- Final Approval Date:
- 09/15/2023