CAPTION
Requesting approval of Change Order No. 1 for an increase in the amount of $64,700.00 and two (2) additional construction calendar days, in connection with the project "Jackson Rd Drain Ph II -2018 Bond Referendum Project No. 16'', Contract No. C-HCDD1-23-026-06-30, with RDH Site & Concrete, LLC, as recommended by Project Engineer, Quintanilla Headley and Associates (Subject to compliance with HB-1295).
BACKGROUND
Project completion date as per CO-1, May 12, 2024
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 12/08/2023 05:18 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 12/06/2023 10:26 AM
- Final Approval Date:
- 12/08/2023