AI - 93559
7.D.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 12/12/2023
- Submitted For:
- Omar Anzaldua Jr.
- Submitted By:
- Enriqueta Zambrano
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Requesting approval of Change Order No. 3, reflecting a increase in the amount of $157,035.90 and thirty (30) additional construction calendar days, for "Mid-Valley Airport Ditch 18B Drainage Improvements - 2018 Bond Referendum Project No. 19’', Contract No. C-HCDD1-22-020-05-31, with Mor-Wil, LLC, as recommended by Project Manager, B2Z Engineering, LLC.
BACKGROUND
Project completion date as per Change Order 3, January 20, 2024.