AI - 95485
8.A.
DD-REGULAR AGENDA REGULAR MTG
- Meeting Date:
- 05/28/2024
- Submitted By:
- Alvaro Chuc
- Department:
- DRAINAGE DISTRICT
CAPTION
South Main Drain Phase 1 - Budget 703
Approval of Application for Payment No. 2 in the amount of $256,689.00 from RG Enterprises, LLC DBA G&G Contractors pertaining to construction contract C-HCDD1-23-053-10-31 South Main Drain Phase 1. Project Engineer HCDD1 Omar Anzaldua, Jr. PE, CFM. PO#648721
Approval of Application for Payment No. 2 in the amount of $256,689.00 from RG Enterprises, LLC DBA G&G Contractors pertaining to construction contract C-HCDD1-23-053-10-31 South Main Drain Phase 1. Project Engineer HCDD1 Omar Anzaldua, Jr. PE, CFM. PO#648721
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 05/24/2024 04:28 PM |
- Form Started By:
- Alvaro Chuc
- Started On:
- 05/24/2024 11:35 AM
- Final Approval Date:
- 05/24/2024