AI - 95592
2.A.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 06/11/2024
- Submitted For:
- Raul Sesin
- Submitted By:
- Justin Silva
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of approved and fully executed Change Order No. 7 reflecting forty-five (45) additional days, for the project "Mile 9 N. & FM 1015 -Package 1B Improvements-2018 Bond Referendum Project No. 24'', Contract No. C-HCDD1-21-054-01-11 -with Mor-Wil, LLC, as
recommended by Project Engineer, Halff Associates, Inc. and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.
recommended by Project Engineer, Halff Associates, Inc. and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.
BACKGROUND
Fiscal Impact