CAPTION
Requesting approval of Change Order No. 1, reflecting an increase in the amount of $90,378.09 and 392 additional construction calendar days for the project "Mile 10 N. & Baseline Rd Phase II - USIBWC Structure 139 - 2018 Bond Project No. 20", Contract No. C-HCDD1-23-014-06-13, with RBM Contractors, LLC, as recommended by Project Engineer, Quintanilla, Headley & Assoc., Inc.