CAPTION
Ratification of approved and fully executed Change Order No. 11, for the project "Jackson Rd Drain Phase I -2018 Bond Referendum Project No. 16’’, to reflect a decrease of ($3,149.31) to Contract No. C-HCDD1-20-034-08-11, with RG Enterprises, LLC dba G&G Contractors, as recommended by Project Engineer, B2Z Engineering, LLC.
BACKGROUND
Fiscal Impact
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 02/14/2025 03:21 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 02/14/2025 11:46 AM
- Final Approval Date:
- 02/14/2025