Esenjay Oil & Gas, LTD.:
Install and maintain a 4" gas pipeline. Begin at Curry Rd and proceed east in the county right-of-way adjacent to Curry Rd, turn south on Dillon Rd and proceed in the county right-of-way adjacent to Dillon Rd, then turn west on Curve Rd, bore under Curve Rd and proceed south in the county right-of-way adjacent to Dillon Rd, bore under Anderson Rd, continue south in the county right-of-way adjacent to Dillon Rd, turn west on Canton Rd and proceed in the county right-of-way adjacent to Canton Rd.
Install and maintain a 4" gas pipeline. Begin at Curry Rd and proceed east in the county right-of-way adjacent to Curry Rd, turn south on Dillon Rd and proceed in the county right-of-way adjacent to Dillon Rd, then turn west on Curve Rd, bore under Curve Rd and proceed south in the county right-of-way adjacent to Dillon Rd, bore under Anderson Rd, continue south in the county right-of-way adjacent to Dillon Rd, turn west on Canton Rd and proceed in the county right-of-way adjacent to Canton Rd.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Lopez | 06/24/2008 03:01 PM |
| Auditor's Office | lfong | 06/25/2008 02:14 PM |
| Court Administrator | Alejandro Garcia | 06/25/2008 02:52 PM |
- Form Started By:
- Saul Garcia
- Started On:
- 06/20/2008 03:46 PM
- Final Approval Date:
- 06/25/2008