CAPTION

Ratification of the fully executed Change Order No.3, reflecting an increase in the amount of $24,927.40 and an additional forty-five (45) calendar days for the project ''Southwest Weslaco -2018 Bond Referendum Project No. 35 '', Contract No. C-HCDD1-23-056-11-14, with Mor-Wil, LLC, as recommended by Project Engineer, Omar Anzaldua Jr., PE, CFM, PMP, CCM, and as approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM

BACKGROUND

CO-3: Project end date 1-25-2025

Fiscal Impact