CAPTION
Ditch W-01-00 Gates Structure - Budget 025
1. Approval and acceptance of Certificate of Substantial Completion and Certificate of Construction Completion from Mor-Wil, LLC pertaining to Construction Contract C-HCDD1-23-008-04-04 Ditch W-01-00 Gates Structure. Project Engineer HCDD1 Omar Anzaldua, Jr., PE, CFM PO#648479
2. Approval of Application for Payment No. "Retainage" in the amount of $107,340.43 with $563.11 in interest from Mor-Wil, LLC pertaining to Construction Contract C-HCDD1-23-008-04-04 Ditch W-01-00 Gates Structure. Project Engineer HCDD1 Omar Anzaldua, Jr., PE, CFM PO#648479
1. Approval and acceptance of Certificate of Substantial Completion and Certificate of Construction Completion from Mor-Wil, LLC pertaining to Construction Contract C-HCDD1-23-008-04-04 Ditch W-01-00 Gates Structure. Project Engineer HCDD1 Omar Anzaldua, Jr., PE, CFM PO#648479
2. Approval of Application for Payment No. "Retainage" in the amount of $107,340.43 with $563.11 in interest from Mor-Wil, LLC pertaining to Construction Contract C-HCDD1-23-008-04-04 Ditch W-01-00 Gates Structure. Project Engineer HCDD1 Omar Anzaldua, Jr., PE, CFM PO#648479
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 03/28/2025 04:37 PM |
- Form Started By:
- Alvaro Chuc
- Started On:
- 03/27/2025 03:58 PM
- Final Approval Date:
- 03/28/2025