North Main Drain TDEM- Budget 204
1. Approval and acceptance of Certificate of Substantial Completion and Certificate of Construction Completion from Welch Excavation pertaining to Construction Contract C-HCDD1-22-066-05-02 North Main Drain. Project Engineer HCDD1 Omar Anzaldua, Jr., PE, CFM PO#647845
2. Approval of Application for Payment No. "Retainage" in the amount of $218,727.94 and $4,728.00 in interest from Welch Excavation pertaining to Construction Contract C-HCDD1-22-066-05-02 North Main Drain. Project Engineer HCDD1 Omar Anzaldua, Jr., PE, CFM PO#647845
1. Approval and acceptance of Certificate of Substantial Completion and Certificate of Construction Completion from Welch Excavation pertaining to Construction Contract C-HCDD1-22-066-05-02 North Main Drain. Project Engineer HCDD1 Omar Anzaldua, Jr., PE, CFM PO#647845
2. Approval of Application for Payment No. "Retainage" in the amount of $218,727.94 and $4,728.00 in interest from Welch Excavation pertaining to Construction Contract C-HCDD1-22-066-05-02 North Main Drain. Project Engineer HCDD1 Omar Anzaldua, Jr., PE, CFM PO#647845
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 04/11/2025 04:26 PM |
- Form Started By:
- Alvaro Chuc
- Started On:
- 04/11/2025 08:32 AM
- Final Approval Date:
- 04/11/2025