Information

CAPTION

Requesting approval of Change Order No. 2, reflecting an increase in the amount of $80,492.03 and 60 additional construction calendar days for the project "Mile 10 N. & Baseline Rd Phase II USIBWC Structure 139 -2018 Bond Project No. 20", Contract No. C-HCDD1-23-014-06-13, with RBM Contractors, LLC, as recommended by Project Engineer, Quintanilla, Headley & Assoc., Inc.