AI - 99170
5.E.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 04/29/2025
- Submitted For:
- Omar Anzaldua Jr.
- Submitted By:
- Justin Silva
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of approved and fully executed Change Order No.3, reflecting 55 additional calendar days for the project ''South Main Drain Channel Improvements Project Phase I -2023 Bond Referendum Project No. 3'', Contract No. (C-HCDD1-23-053-10-31), with RG Enterprises, LLC dba G&G Contractors, as recommended by Project Engineer, Assistant District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM and approved by District General Manager, Raul E. Sesin, PE, CFM.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 04/25/2025 04:02 PM |
- Form Started By:
- Justin Silva
- Started On:
- 04/22/2025 09:49 AM
- Final Approval Date:
- 04/25/2025