AI - 99531
4.A.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 05/29/2025
- Submitted For:
- Yvette Barrera
- Submitted By:
- Enriqueta Zambrano
- Department:
- DRAINAGE DISTRICT
CAPTION
Ratification of approved and fully executed Change Order No.3, reflecting an increase in the amount of $8,544.28 for the project ''South I Rd East Side Drainage Improvements -2018 Bond Referendum Project No. 33'', Contract No. C-HCDD1-22-029A-08-09, with RBM Contractors, LLC, as recommended by Project Engineer, B2Z Engineering LLC and approved by District General Manager, Raul E. Sesin, PE, CFM.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 05/23/2025 01:44 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 05/21/2025 11:55 AM
- Final Approval Date:
- 05/23/2025