SUBJECT: AUTHORIZATION OF THE EXPENDITURE OF CONSTRUCTION FUNDS FOR APPROVED CIP PROJECT #42061 – TRAFFIC SIGNAL 152ND AVENUE AND VAN BUREN STREET
 
STAFF PRESENTER(S): Steve Scinto, Director of Engineering

OTHER PRESENTER(S):

David Jossund, Sr. Project Manager

SUMMARY

A request to authorize the expenditure of construction funds up to $1,396,700 for Capital Improvement Program (CIP) Project #42061 – Traffic Signal152nd Avenue and Van Buren Street.

STRATEGIC PLAN ALIGNMENT

     

RECOMMENDATION

Authorize the expenditure of construction funds up to $1,396,700 for Capital Improvement Program (CIP) Project #42061 – Traffic Signal 152nd Avenue and Van Buren Street. (Steve Scinto, Director of Engineering)

FISCAL IMPACT

CIP Project #42061 – Traffic Signal-152nd Avenue and Van Buren Street is currently programmed in the FY2025-FY2029 CIP with a total project budget of $1,425,000 with an estimated completion date of June 2025.

BACKGROUND AND PREVIOUS ACTIONS

Per City of Goodyear Resolution 08-1255, all expenditures of budgeted funds in excess of $500,000 must obtain Council approval.

On June 6, 2022 (AI-806), Council approved CIP #42061 – Traffic Signal-152nd and Van Buren in the adoption of Resolution No. 2022-2253 Determining and Adopting the Final Estimates of Proposed Revenues and Expenditures for the city of Goodyear for FY2023.

On June 12, 2023 (AI-1537), Council approved the carryover of CIP #42061 – Traffic Signal-152nd and Van Buren in the adoption of Resolution No. 2023-2318 Determining and Adopting the Final Estimates of Proposed Revenues and Expenditures for the city of Goodyear for FY2024.

On June 10, 2024 (AI-1797), Council approved the carryover of CIP #42061 – Traffic Signal-152nd and Van Buren in the adoption of Resolution No. 2024-2381Determining and Adopting the Final Estimates of Proposed Revenues and Expenditures for the city of Goodyear for FY2025.

In October 2022, Goodyear selected Dibble from the on call list to complete design activities for CIP Project #42061 – Traffic Signal-152nd and Van Buren with a contract not to exceed $53,814.00.

In July 2024, Goodyear selected Talis from a cooperative Job Order Contract (JOC) list to complete construction activities for CIP Project #42061 – Traffic Signal-152nd and Van Buren with a contract not to exceed $565,737.63.

STAFF ANALYSIS

CIP Project #42061 – Traffic Signal-152nd and Van Buren will provide final construction services. In general, the proposed improvements include updated ADA ramps, intersection pathways and installation of traffic signals.