| ITEM #: 9. DATE: 08/30/2021 AI #:423 |
![]() |
CITY COUNCIL ACTION REPORT
| SUBJECT: | ESTRELLA PARKWAY AND ESTRELLA FOOTHILLS HIGH SCHOOL TRAFFIC SIGNAL |
| STAFF PRESENTER(S): | Hugh Bigalk, P.E., City Traffic Engineer |
OTHER PRESENTER(S):
Troy Tobiasson, Senior Project Manager
SUMMARY
Request Council approve the budgeted expenditure of $865,000 for traffic signal equipment and construction for traffic signal construction at Estrella Parkway & Estrella Foothills High School.
Recommendation
Approve expenditure of funds in the amount of $865,000 for the construction of a traffic signal at the intersection of Estrella Parkway & Estrella Foothills High School. (Hugh Bigalk, P.E., City Traffic Engineer)
FISCAL IMPACT
The cost of the traffic signal construction at Estrella Parkway & Estrella Foothills High School is budgeted in the FY2022 Capital Improvement Program (CIP) under Project 42021 with an approved budget of $865,000.
BACKGROUND AND PREVIOUS ACTIONS
In 2020, the intersection was programmed into the FY2021-2025 CIP with design to be performed in FY2021 and construction to be completed in FY2022. Design was completed in FY2021.
STAFF ANALYSIS
Construction of the project is scheduled to begin in September 2021 and be completed by the end of February 2022.